![A giant crane helps put a segment of concrete into place as part of the formation of a tunnel at Wangaratta railway station. Part of the platform was cut away to allow for the installation. Picture supplied by ARTC A giant crane helps put a segment of concrete into place as part of the formation of a tunnel at Wangaratta railway station. Part of the platform was cut away to allow for the installation. Picture supplied by ARTC](/images/transform/v1/crop/frm/XJLgPnEdnKaFugZzKyL6Sw/2f542b8f-e9ca-43b5-94b1-847fe48645ea.jpg/r0_0_5315_3543_w1200_h678_fmax.jpg)
A FRESHLY formed section of platform is the most visible clue that a pedestrian tunnel now sits below the Wangaratta railway station yard.
Subscribe now for unlimited access.
or signup to continue reading
A 24-metre chunk of the boarding area south of the station had to be cut away to allow the trench to be formed into which 30 concrete segments were laid.
A 750-tonne crane was needed to manoeuvre the pieces into place.
They have been subsequently covered and a new concrete-bounded section of platform created to reconnect temporarily separated sections.
At the same time a section of railway track was lifted and then returned by a 250-tonne crane.
![Workers finish of the formation of a new section of platform laid over the underpass sitting below the surface. Workers finish of the formation of a new section of platform laid over the underpass sitting below the surface.](/images/transform/v1/crop/frm/XJLgPnEdnKaFugZzKyL6Sw/89ba1b3e-3afd-4e96-99bc-d94e1c4ded5d.jpg/r0_109_1170_767_w1200_h678_fmax.jpg)
Works will occur at a later date to form entrances to the tunnel which will replace the former Cusack Street footbridge.
A 750-tonne crane was also used to hoist 16 precast concrete beams on to pylons and form the bridge within sight of where the Kelly Gang siege occurred in 1880.
![Beams are lowered into place to help form the deck of the new bridge across the railway line at Glenrowan. Picture supplied by the ARTC. Beams are lowered into place to help form the deck of the new bridge across the railway line at Glenrowan. Picture supplied by the ARTC.](/images/transform/v1/crop/frm/XJLgPnEdnKaFugZzKyL6Sw/b4d01cb4-96ed-48f6-94e6-26bd95f21d67.jpg/r0_272_5315_3272_w1200_h678_fmax.jpg)
The project close to Wodonga Council's Logic centre involved the removal of the equivalent of five Olympic swimming pools of soil to lower the track by up to 2.5 metres.
Then 2000 tonnes of stone ballast was put in place and 800 concrete sleepers and 800 metres of rail laid.
To allow the changes to proceed the Australian Australian Rail Track Corporation and contractor McConnell Dowell were given possession of the track for 60 hours from Saturday September 23 to the following Monday.
IN THE NEWS:
- Pigeons forward suffers serious facial injuries in premiership celebrations
- 'I wouldn't change anything': Border GP retires after 45 years
- Two-car crash causes delays to morning traffic in Albury
- Woman brazenly stole from Kmart two days in a row despite staff attempts to stop her
- How those in North East see Andrews' departure
- Going, going, nearly gone: Pine trees get the chop
That meant no freight trains and passenger services being replaced with buses and no trains stopping at Wangaratta for much of this week.
The track corporation's Victorian and South Australian general manager projects Ed Walker was pleased with how the around-the-clock effort unfolded.
![The extent of the new ballast, sleepers and rails is clear in this image showing the work done to lower the trajectory of the line below the Murray Valley Highway at Barnawartha North. Picture supplied by the ARTC The extent of the new ballast, sleepers and rails is clear in this image showing the work done to lower the trajectory of the line below the Murray Valley Highway at Barnawartha North. Picture supplied by the ARTC](/images/transform/v1/crop/frm/XJLgPnEdnKaFugZzKyL6Sw/e56c004b-3a69-4fa0-93dd-ff794e3d28df.jpg/r0_272_5315_3544_w1200_h678_fmax.jpg)
"It was a successful possession with all our planned construction works completed," Mr Walker said.
"Importantly, the ARTC Inland Rail team and our contractors McConnell Dowell delivered the work safely.
"We work hard to keep the disruption around the sites to a minimum and we thank the local communities for their patience and understanding as we carry out the construction tasks."
To read more stories, download The Border Mail news app in the Apple Store or Google Play.
Our journalists work hard to provide local, up-to-date news to the community. This is how you can continue to access our trusted content:
- Bookmark https://www.bordermail.com.au/
- Make sure you are signed up for our breaking and regular headlines newsletters
- Follow us on Twitter: @bordermail
- Follow us on Instagram @bordermail
- Follow us on Google News